Fictional worked example

Project status report example: RAG, forecast, and decisions

A fictional weekly project status report with an explained RAG rating, completed work, forecast, blockers, owners, and a specific sponsor decision.

The reporting context

This is a fictional service-portal pilot, not a customer report. Reporting period: 8 to 12 June 2026. Report date: 12 June 2026. Audience: internal delivery review and sponsor. Planned pilot handover: 30 June 2026. Every date and outcome is an invented part of the worked example, not this page’s publication date.

The purpose is to explain what changed, what is forecast, and which decision is needed. A percentage-complete figure alone would conceal the unresolved supplier dependency.

Executive summary and RAG rationale

Overall health: yellow / at risk. The pilot scope remains achievable, but supplier sandbox access is not confirmed. Without access by 16 June, end-to-end acceptance testing will slip by up to five working days. No revised handover date has been approved.

For this fictional team, green means the agreed milestone is forecast within tolerance; yellow means delivery is threatened but a recovery path exists; red means the milestone is blocked or outside agreed tolerance and needs intervention. These are team criteria. The project manager selects the report health in Meridian; it is not an automatic prediction from task progress.

Completed this period

Integration lead: completed stub-interface tests for three priority journeys on 10 June. Data lead: validated the 50-record sample on 11 June and assigned corrections for two mandatory-field mappings. Adoption lead: confirmed eight pilot participants on 12 June.

Evidence for the delivery review would be the test log, mapping review, and participant confirmation. This example describes those records but does not invent live attachments, screenshots, or customer results.

Forecast and next period

Forecast: retain 30 June as the working handover target, conditional on supplier access by 16 June and successful end-to-end testing by 23 June. Confidence is limited until that dependency is resolved. This is a forecast with assumptions, not a promise.

Next period: integration lead to run end-to-end tests by 19 June if access arrives; data lead to retest the two mappings by 17 June; project manager to review acceptance evidence with the sponsor on 23 June. If access misses 16 June, reforecast before committing to a new date.

Blocker, risk, and decision required

Current blocker: sandbox credentials have not been supplied; owner: integration lead; next action: supplier escalation on 15 June. Linked risk R-01 covers the possible schedule consequence. Keep the actual access issue distinct from the uncertain delivery impact.

Decision needed from sponsor by 16 June: approve a reduced pilot covering the three tested journeys if full access is still unavailable, or retain full scope and authorize a revised handover forecast. Recommendation: retain full scope until the access deadline, then decide using test evidence. Record the decision and owner rather than presenting the recommendation as approval.

Prepare the right version for the audience

An external version could summarize the milestone exposure and agreed next update while omitting internal supplier negotiation details. Internal and external are communication labels, not security controls. Review permissions and the text before sharing; changing the label is not a substitute for access control.

In Meridian, author a dated report, choose health and communication type, optionally associate a cycle, select relevant sections, and write forecast and blocker notes. Reports remain in project history and can be copied as formatted plain text. This does not claim PDF export, automatic distribution, or a generated executive narrative.

Before sending the next update

Check that the period, baseline, RAG rationale, changed forecast, action owners, decision deadline, and next update are explicit. Do not silently change last week’s baseline to make the new report look green. Link material risk exposure back to the register.