Fictional worked example

Risk register example: scoring, responses, and review

A fictional risk register example with probability and impact scores, owners, triggers, responses, residual risk, and review decisions.

The fictional project and the risk statement

This teaching example follows a fictional service-portal pilot. All people, dates, scores, and outcomes below are invented, not customer evidence. The pilot has a planned handover on 30 June 2026 and depends on a supplier sandbox and an internal data owner.

R-01: Because supplier sandbox access is not confirmed, integration testing may start late, delaying pilot acceptance by five working days. This is a risk because the delay is uncertain. If the promised access date passes without access, record the actual blocker as an issue and link it to the risk; do not keep describing an event that has already happened as uncertain.

A small worked register

R-01 | Supplier access delay | Owner: integration lead | Probability 4 | Impact 4 | Score 16 | Response: mitigate | Status: open. Trigger: no written access confirmation by 9 June. Action: request confirmation by 5 June and prepare a stub interface by 8 June.

R-02 | Data mapping errors | Owner: data lead | Probability 3 | Impact 4 | Score 12 | Response: mitigate | Status: open. Trigger: more than two mandatory fields fail the sample validation. Action: review a 50-record sample with the data owner before migration rehearsal.

R-03 | Low pilot attendance | Owner: adoption lead | Probability 2 | Impact 3 | Score 6 | Response: accept with contingency | Status: monitoring. Trigger: fewer than eight confirmed pilot participants by 12 June. Action: retain a reserve participant list and agree a smaller pilot decision with the sponsor if the trigger fires.

Define the scale before comparing scores

For this example only, probability uses 1 rare, 2 unlikely, 3 possible, 4 likely, and 5 almost certain. Impact uses schedule delay: 1 less than one working day, 2 one to two days, 3 three to four days, 4 five to nine days, and 5 ten or more days. Agree different anchors if cost, safety, quality, or compliance is the governing concern.

Score = probability × impact, using whole numbers from 1 to 5. R-01 is 4 × 4 = 16. This team reviews scores 15 to 25 with the sponsor, 8 to 14 at the weekly delivery review, and 1 to 7 with the owner. These are fictional team thresholds, not universal PMBOK rules or automatic Meridian escalation settings.

Choose a response that changes the exposure

Avoid changes the plan to remove the threat; mitigate reduces probability or impact; transfer allocates an agreed part of the exposure to another party; accept retains it with an explicit decision. Merely naming an owner is not a response. For R-01 the stub allows partial testing while the supplier dependency remains.

Record the action owner, due date, trigger, and evidence separately from the score. In Meridian, use the risk owner and response fields and supporting notes for the agreed controls and trigger. This guide does not imply dedicated automated trigger or residual-risk calculation features.

Review residual risk and make a decision

Fictional review, 10 June 2026: the integration lead demonstrates passing stub tests, but supplier access is still unconfirmed. The team estimates residual probability 3 and impact 3, giving 9. Residual means the exposure expected after the controls, not an automatic reduction because an action was marked done.

Decision: keep R-01 open, escalate the missing confirmation to the sponsor, and review again on 12 June. The sponsor owns the decision about moving pilot acceptance; the integration lead owns the next action. Close the risk only when the exposure has expired or an explicit acceptance decision and its rationale are recorded.

Use the example in a project review

Bring the highest-priority risks, evidence of completed responses, changed assumptions, and decisions needed. Copy the structure, not the fictional scores. In a status report, summarize the schedule exposure and the decision required, then link back to the maintained register.